Hollywood, California
New 4,800 s.f. gym using existing walls. Cost: $2.6 Million, Complete 2016

Project included inserting a new steel structure inside an existing masonry building. This enabled a ceiling line 12’ higher than the original, and created an entire new play space.

Work also included a new wood gym floor, retractable basketball hoops, scoreboard, ADA access, concrete filled metal deck roof, HVAC system, lighting system, main electrical service, windows throughout the entire facility, and exterior finishes including added steel canopies. All work was done while the children and staff continued to use the surrounding facilities, so safety and coordination were key elements to the Project.